ONGOING ASSIGNMENTS
Below is a selection of ongoing assignments performed by RANGMAR Management’s consultants.
The West Link E03 Kvarnberget, The Swedish Transport Administration
Project manager for The West Link sub-project E03 Kvarnberget with responsibility for the project’s finances and contract as well as for the management of the Swedish Transport Administration’s client organization. Subsection E03 Kvarnberget consists of a 560m double-track railway tunnel adjacent to subsections E02 Centralen and E04 Haga. The shaft for the train tunnel is carried out in 200m with top-down technology in soil and in 360m with cut-and-cover technology in rock. The contract also includes a 110m long service tunnel in rock, a service shaft and two passages over the Göta tunnel where reinforcements of the existing tunnel construction will be carried out.
COMPLETED ASSIGNMENTS
Our consultants have good experience in civil engineering and know what is required for a project to achieve set goals and desired results. We handle the entire project cycle from idea to final inspection.
Below is a selection of successful assignments completed by RANGMAR Management’s consultants.
The West Link E02.FA33 Time-critical work Götatunnel reinforcement work, Swedish Transport Administration
Project manager and design coordinator for Västlänken’s preparatory work E02.FA33 where the Götatunnel was reinforced at its two crossing points with The West Link train tunnel. The contract also included a permanent traffic diversion of Västra Sjöfarten prior to the start of construction of The West Link sub project E03 Kvarnberget, as well as a reconstruction of The Götatunnel’s operating area DU5 as a result of its locational conflict with The West Link.
Final construction inspections, Alingsås municipality
Construction inspectors for several final construction inspections within land and construction were provided to Alingsås municipality for various types of construction contracts. Call-offs took place continuously on the current framework agreement, which extended from 2018 until the year 2023.
Hossaberget, Partille municipality
Project management for the planning of public land within the development area Hossaberget in Öjersjö consisting of 240 homes. The construction included work with streets, piping, street lighting and geotechnical investigation. The assignment also included producing of bill of quantities, technical description, production cost estimate and administrative regulations.
The South West Link, Svenska Kraftnät
Deputy project manager for all ground work in the South West Link, project planning of approx. 250 km of underground high-voltage cables from Hurva to Barkeryd. The assignment also included the rerouting of existing cables and the design of roads. Responsible for coordination between the project’s five design blocks for cable shafts, review coordination of construction documents and as built drawings as well as questions during the construction period for all blocks and construction contracts.
Bana Väg I Väst E42, Swedish Transport Administration
Construction management contract E42 which was part of the Bana Väg i Väst project with the aim of expanding the four-lane motorway and double track between Gothenburg and Trollhättan. Contract E42 consisted of 1,500 meters of reconstruction of a local street, new installation of piping, electricity and opto as well as upgrading of Surte Torg. Contract sum approx. SEK 60 million.
Framework contract procurement for trenchless pipeline renovation, Lerum municipality and others
Responsible for producing request documents for the procurement of framework agreements regarding contracts for trenchless pipeline renovation on behalf of Lerum municipality together with Alingsås municipality, Härryda municipality, Marks municipality, Mölndal city and Partille municipality.
Stenbrottet, Härryda municipality
Stenbrottet, Härryda municipality
Project management for the design of streets and pipelines for exploitation area Stenbrottet in Härryda municipality. The construction included streets, a roundabout, two double bus stops as well as noise protection measures as well as opto, pipings and street lighting for the new residential area. The assignment also included producing administrative regulations, bills of quanteties, technical descriptions and production cost calculations for the costruction contract.
Södra Vägen and Berzeliigatan, Gothenburg City Traffic Office
Project management for the design of pedestrian and biking tracks in an inner-city environment along Södra Vägen between Korsvägen and Heden and along Berzeliigatan in central Gothenburg. Also responsible for producing administrative regulations, bills of quanteties and technical descriptions for the construction contract.